October 29, 2026
At an April 27, 2026 joint meeting of Missouri City's City Council and Planning and Zoning Commission, Planning and Zoning Commissioner Atwood described a recent Thursday on Sienna Parkway. Getting from around Waters Lake Boulevard and Scanlan Trace over to Steep Bank Trace took an hour and ten minutes, for a distance he put at less than two miles. "Traffic in there at rush hour times," he said, "it's bedlam."
Five months later, on Sept. 21, City Council approved a deal meant to fix that drive. Community Impact covered the vote three days later. The deal does add capacity. It also does a second job that matters just as much for anyone who drives Sienna Parkway every day. The new roads are the city's condition for letting new homes get built again, so the relief and the added traffic are scheduled to show up together. The stretch the city itself calls the bottleneck is fixed last.
The stretch from the commissioner's story is the one the city's plans keep coming back to. At the same April meeting, Atwood said it outright: "The choke point in Sienna for traffic flow is from Steep Bank Trace to Scanlon Trace." The railroad tracks run between those two intersections.
A commissioner asked what the current level of service on Sienna Parkway is. The staff answer was short: "Current service is not good." Staff added that widening Sienna Parkway "still provides one way in and one way out," and said the city was also studying alternate routes "both for mobility as well as emergency access."
That framing explains the shape of the September deal. Adding lanes over the tracks helps the chokepoint. New connections to FM 521 give drivers somewhere to go besides that chokepoint. The deal does both, on different timelines and with different parties paying.
The agreement is among Missouri City, Toll-GTIS Property Owner, LLC, which is Toll Brothers, and Sienna Municipal Utility District No. 5. In the agreement, the larger Toll project is called "Sienna South," about 3,700 acres. One piece of it was already in the pipeline before the vote. A Toll-GTIS concept plan on the Aug. 12, 2026 Planning and Zoning Commission agenda, labeled Sienna Concept Plan 4C, covers 237.34 acres, sections 75 through 80, Regency Lakes Drive and Sienna Parkway Phase 7, and shows 375 residential lots.
According to Community Impact's report, City Attorney E. Joyce Iyamu said city staff had not been approving new developments in Sienna because they recommended dealing with traffic circulation first. Public Works Director Mustafa Albassam said the road improvements would allow developers to keep building homes in the area. He described the logic this way in the same article:
"Anticipating what the future will bring, you need to have capacity and alternate routes for the residents to use."
So the roads and the rooftops are tied together by design. The pause on new approvals gave the city its leverage, and the roads are what it got in return. A Planning and Zoning commissioner made the same point back in April. He said the land out to FM 521 is going to be developed, and any fix has to account for "the additional traffic that's going to come once that is built out."
Missouri City's Oct. 2 press release lays out the sequence. The funding schedule comes from Community Impact.
The first two items are deadlines written into the developer agreement. The fourth is described as "currently projected," which makes it an estimate. That gap matters for the daily drive. The routes to FM 521 should help trips headed south and east before the Steep Bank Trace to Scanlan Trace North stretch gets any wider. Trips that have to cross the tracks get their extra lanes about two years later. Albassam told Community Impact that past work focused on improving individual chokepoint intersections, and this plan focuses on connectivity instead. "Each single one of the projects is literally just one piece of the puzzle," he said.
The deal also changes the long-range plan, and that matters most to residents along a few specific streets. Alongside the agreement, Council amended the Major Thoroughfare Plan. Once the new segments are built, two previously proposed north-south routes come out. Those are Route 2, which would have run from Sienna Lakes Drive by way of Crown Ridge Drive and Broussard Lane to Fenn Road, and Route 3, which would have run from Sienna Lake Drive by way of Cottage Place and Gussie Mae Lane to Fenn Road. Removal depends on construction. It takes effect after the specified Route 1 segment on Toll's land and the four Sienna Parkway lanes from Waters Lake Boulevard to FM 521 are built.
Neighborhood streets had come up before. At the April hearing on an earlier, broader draft, a Sienna resident said some of the alternatives could push heavy traffic onto narrow neighborhood streets. Other speakers raised similar concerns about a proposed New Point Drive and McKeever connection. The approved package moves the long-range plan toward the new FM 521 connections instead.
One more connection is possible but far from certain. The agreement opens a path for a north-south link between Park Crossing Drive and One Oak Chase Road, which would lead toward Fenn Road and FM 521. Because it crosses several jurisdictions, it still needs right-of-way acquisition, Fort Bend County sign-off, City of Arcola approval and city authorization.
Two ideas from the city's May thoroughfare update are further out. The Bees Passage Bridge would run from Sienna Ranch Road north to Sienna Parkway east. The Miller Road connector would run from Waters Lake Boulevard south across the levee to Miller Road. Community Impact's May report lists both as short-term concepts, one to five years out. Each still needs feasibility work, funding, land, design and construction.
None of the September deal shows up on the road this fall. Through mid-November, here is what is actually on the calendar.
That leaves the Dec. 31, 2027 deadline as the first date with a binding commitment behind it. Construction of the Phase 7 lanes and the Sienna Lakes Drive extension, along with new homes in the sections around them, should be the next visible signs that the plan is moving. The city points residents to its Sienna Mobility Improvements page for project updates.
If you're wondering how the new routes to FM 521 and the 2029 crossing widening could affect a particular street or section of Sienna, Jaime Dossett follows these projects closely and is glad to talk them through with you. Schedule your free neighborhood consultation, and bring the drive you'd like to see get shorter.